Every month is a lease that has not started
A finished data hall with no power is the most expensive empty building there is. Take 50 MW of IT capacity leased at around $150 per kilowatt per month: that is roughly $7.5 million of revenue a month, and every month of delay is a month that does not come back. (Illustrative figures; your rates will differ.)
The electrical package is usually what sets that date. Transformers, switchgear and generators have long lead times, so a rating that turns out wrong after the order is placed is not a redline. It is a new delivery date.
The return on design review is time: catching the wrong rating while it can still be fixed on the drawing.
Start from the promise
Every data center design makes one promise that everything else follows from: how much backup the site has. N+1 means one spare beyond what the load needs; 2N means a full second system. Generator count, UPS count and transformer sizing are all that promise applied to a design load.
So the first check is simple arithmetic, done honestly: the number of units times their rating, against the load, at the promised level of backup. Most misses are not wrong math. They are the right math applied to an old load figure or an earlier phase of the campus.
Fail· Generator plant covers design load at N+1
The generator schedule lists 22 × 3,000 kW units (66 MW), but the load calculation shows 67.4 MW of critical and mechanical load. N+1 at that load needs 24 units. Add units or confirm the load basis.
↳ E-601 Generator schedule, p. 2↳ Load calculation, p. 7
The worst fault happens with everything on
The highest fault current on a campus usually is not the normal case. It is the moment when the utility and a bank of generators are connected at the same time, for example during a transfer, and both can feed a fault. Switchgear that is comfortably rated for the utility alone can come up short.
The check is whether the study covers every way the system is allowed to run, and whether each piece of gear is rated for the worst of them. It is cheap to confirm on paper and very expensive to discover after the gear is built.
One rating, four documents
Many engineers and vendors contribute to a campus design, and the same rating gets written down in each of their documents. When one changes, the others lag behind.
| Document | Module rating | Battery runtime |
|---|---|---|
| Electrical one-line | 1,250 kVA | — |
| Equipment schedule | 1,250 kVA | 5 min |
| Basis of design | 1,000 kW | 5 min |
| Battery sizing calc | 1,250 kVA | 3.8 min |
Some disagreements are only units: kVA and kW can both be right and still not describe the same module. Others are real, like a battery that holds the load for less time than the design assumes. A review has to read the units as well as the numbers.
Backup power is a sequence
When the utility drops, the generators start, synchronize and pick up the load in steps, and the batteries carry everything until they do. The batteries have to last through the slowest credible version of that sequence, including a generator that fails to start the first time, and they have to do it when they are old, not new.
- Battery runtime at end of life, against the longest transfer the design allows.
- Generator load steps, against what the generators can actually pick up.
- Fuel on site, against the runtime the design promises.
What this means for your schedule
The agent runs your checklist against every document in the project and writes each finding with its source pages cited, so your engineers can confirm it in seconds. It is strongest on electrical and power, where it was built; it will run mechanical and cooling checklists too, and you should judge those results yourself.
It does not replace the engineer of record. It does the cross-referencing across every package and revision, so the expensive mismatches surface while they are still lines on a drawing and not dates on a schedule.
The checklist, condensed
Examples from the checklists teams run on these packages. Bring your own or start from ours; each check comes back Pass, Fail or N/A with the page behind it.
Utility + substation
- Service voltage and capacity consistent across one-line, utility agreement and load letter
- Transformer ratings and impedance vs the short-circuit study
- Protection scheme and relay references complete
- Onsite generation and storage tie-ins shown on the one-line
MV + LV distribution
- Switchgear interrupting and withstand ratings vs available fault current
- Feeder ampacity and derating vs protective devices
- Redundancy (N, N+1, 2N) consistent between one-lines and basis of design
- Arc flash labels and study results aligned
Backup generation
- Generator count and kW vs design load with the stated redundancy
- Fuel storage vs required runtime
- Transfer and paralleling scheme matches the sequence of operations
- Emissions and permit limits reflected in the generator schedule
UPS + critical power
- UPS module ratings and battery runtime vs IT load
- Battery room ventilation, spacing and fire protection
- Grounding and bonding details complete
- Critical power paths match the redundancy narrative
